All services

Fleet charging infrastructure

Charging infrastructure that fits the operation

Fleet electrification stands or falls on charging. We analyse the operation, calculate the charging demand and design infrastructure that supports daily operations without a grid connection larger than it needs to be.

Fleet charging infrastructure

Who it is for

Haulage companies, bus operators, municipalities and anyone running trucks, buses or vans and switching to electric.

What we do

  • Analyse energy and power demand from real driving and dwell times
  • Set up a charging schedule: when, for how long and at what power
  • Decide the number and power of chargers, AC and DC
  • Size the grid connection and handle the dialogue with the grid operator
  • Design the infrastructure: equipment layout on site, transformer stations, cable routes and electrical design
  • Assess shared use with public charging where it makes sense

What you get

A design report with power demand, charging schedule, drawings and cost estimate. A basis you can take straight to tender or construction.

The right chargers, in the right size
How many chargers are needed and the power of each one.
Electrify now, not when the grid catches up
How much of the fleet the existing connection can already carry.
Every departure, fully charged
Vehicles charged and pre-heated before the first trip, summer and winter, planned around the timetable.
Lower power costs, every year
A lower peak means a smaller connection and lower capacity charges.
Room to grow
How many more vehicles the depot can take, and when more capacity is needed.
Ready for the bad day
How the operation copes when a charger fails or a vehicle returns late, and how much margin there is.

Phased build-out

The grid connection is sized for the final stage from the start, civil works and cable routes are done once, and chargers are added as vehicles arrive. The example below is from a real project for a haulage operator going from 2 to 20 electric trucks.

Example: haulage operator, 2 to 20 electric trucks, charged overnight
PhaseTrucksPeak powerGrid connection
Now2about 70 kW315 A
In 2 years4about 135 kW315 A
Full fleet20about 525 kW900 A

35 kW per connector is enough overnight. Civil works are done once, for the final stage.

Resilience

We test what happens when a charger fails or a vehicle returns late, and how much margin there is before the first departure of the morning is affected.

What you provide

  • Timetable or shift plan
  • Fleet data: battery size and usage
  • Site plan of the depot
  • Electricity tariff

No measurements are needed for a first answer. Most of the work is done remotely and the results are presented in an online meeting.

Get in touch

Send us a timetable and fleet data and we will assess the charging demand. No measurements are needed for a first answer.

Get in touch

Electrifying a fleet?

The first conversation is short and without obligation. Send us a line and we will work out what is needed.

Send an email
Email
enord@enord.is
Phone
840 4935
LinkedIn
Hrafn Leó Guðjónsson
Location
Reykjavík, Iceland