Depot charging infrastructure for 70 electric buses

Design of depot charging infrastructure for 70 electric buses, with 3.5 MW of power, on-site high-voltage distribution and three transformer stations. The work laid the technical basis for procurement.

3.5 MW · 70 buses · 3 transformer stations

Depot charging infrastructure for 70 electric buses

The challenge

Strætó was expanding its electric bus fleet and needed a depot that could charge a large fleet every night. This was not about installing chargers but about megawatts of power, new on-site high-voltage distribution and a charging schedule that kept the buses on time. As a publicly owned company, Strætó needed the solution clearly defined before it could be tendered.

What we did

  • Analysed charging demand from the bus schedule: arrival times, dwell times and energy needs
  • Designed charging infrastructure for 70 buses with 3.5 MW of total power
  • Defined on-site high-voltage distribution and the placement of three transformer stations to minimise losses
  • Allowed for fleet expansion in the design

Outcome

  • Charging infrastructure for 70 buses, 3.5 MW, designed from real operations rather than theoretical peak power
  • High-voltage distribution and three transformer stations on site
  • A ready basis for tendering the charging infrastructure

Lesson

The biggest savings are made at the design stage, before construction starts.

Related services

Have a similar project in mind?

The first conversation is short and without obligation. Send us a line and we will work out what is needed.

Send an email
Email
enord@enord.is
Phone
840 4935
LinkedIn
Hrafn Leó Guðjónsson
Location
Reykjavík, Iceland